Due to ensuing winter weather, having very limited windows of non-rainy days, we chose to pour this 26,200 SF monolithic slab in one crew shift. The job for the day was fielded by 32 laborers, finishers and supervisors; required 680 cubic yards of pre-mixed concrete (68 truck loads), aided by two concrete pumps, a laser screed and three power trowels.